Sohanlal Shankarlal Vishnoi
Deedo IDDD-3BS3Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 12 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vantage-9P52100003199 | Baner | Certificate Signed | 31 Jan 2021 | 31 Jan 2021 | On date |
| VaigaP52100022419 | Chinchwad | Certificate Signed | 30 Dec 2023 | 29 Dec 2024 | +12 mo |
Sohanlal Shankarlal Vishnoi, in questions
Does Sohanlal Shankarlal Vishnoi finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sohanlal Shankarlal Vishnoi registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Sohanlal Shankarlal Vishnoi have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.