SMP Namrata Lotus Landmarks LLP
Deedo IDDD-AY3RNone of 2 registrations has reached its promised completion date yet.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| 6 BoulevardPR1261012600142 | Tathwade | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
| 6 BoulevardPR1261012602504 | Tathwade | Not on record | 30 Dec 2031 | — | On date |
SMP Namrata Lotus Landmarks LLP, in questions
Does SMP Namrata Lotus Landmarks LLP finish projects on time?
None of its 2 MahaRERA registrations has reached its promised completion date yet.
How many projects has SMP Namrata Lotus Landmarks LLP registered with MahaRERA?
1 project under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does SMP Namrata Lotus Landmarks LLP have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.
