Company or firm · first RERA registration 2017

Sigma Realty

Deedo IDDD-FFGB

Of 4 registrations whose promised date has arrived, 1 kept it (25%). The rest ran a median 11 mo late.

Projects34 RERA registrations
Kept RERA date25%Maharashtra: 73%
Median delay11 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
UnnatiP52100000976NereCertificate Signed31 Dec 201831 Dec 2019+12 mo
UnnatiP52100029549NereCertificate Signed31 Dec 202331 Dec 2023On date
UnnatiP52100066546NereCertificate Signed31 Dec 202531 Dec 2025+11 mo*
PragatiP52100076817NereCertificate Signed31 Dec 202531 Dec 2025+11 mo*

Sigma Realty, in questions

Does Sigma Realty finish projects on time?

Of 4 MahaRERA registrations whose promised completion date has arrived, 1 kept it (25%). The rest ran a median 11 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sigma Realty registered with MahaRERA?

3 projects under 4 MahaRERA registrations; 2 completed on MahaRERA.

Does Sigma Realty have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology