Residential / Group Housing · 2 buildings · 90 unitsRERA P52100000976

Unnati

Deedo IDDP-PUN-B7JE

Completion was pushed back 1 year to Dec 2019, and that date has passed too; no MahaRERA orders on record; 13% of its units are booked.

Nere, Pune 412206 · Promoter: Sigma Realty

Delivery7 yrs 10 mo latePromised Dec 2018 · revised Dec 2019 · that date has passed tooRegulatoryNo ordersNot in any MahaRERA list or order Deedo has readSales13% booked12 of 90 units · as the promoter reported to MahaRERA
Unnati project report cardPDF: delivery, regulatory orders, people on record, every tower and the registered deals — for your bank or lawyerSee what's inside · from ₹1,499

Completion was pushed back 1 year to Dec 2019, and that date has passed too

  • This projectRegistered 25 Jul 2017, completion promised 31 Dec 2018, revised to 31 Dec 2019, and still not shown completed today.

1 extension certificate on record.

1 registration · Source: MahaRERA registration and extension certificates

Latest registered deeds

Sales, rentals and mortgages matched to this project · the free view shows a price band

No registered deeds matched to this project yet
Sales, resales, rentals and mortgages appear here once registered documents are matched to it by evidence.

2 buildings

Open a building to see every flat, floor by floor.

Floors and units from the registration certificate annexures and MahaRERA's project page.

Regulatory recordNone found

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

RERA registrationP52100000976
RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210000097625 Jul 201731 Dec 201831 Dec 2019Sigma RealtyProject page
Documents80

2 documents held by Deedo, 78 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardSigma Realty Pan Card.pdf · uploaded 19 Jul 2017Source

Legal

  • Declaration Form BForm B Builder Nere 01.pdf · uploaded 19 Jul 2017Source
  • Legal Title reportTitle Certificate Nere Unnati.pdf · uploaded 19 Jul 2017Source

Migrated

  • 1 PAN CardSigma Realty Pan Card.pdf · uploaded 19 Jul 2017Source
  • 1 Copy of the legal title reportTitle Certificate Nere Unnati.pdf · uploaded 19 Jul 2017Source
  • 1 Details of encumbrancesEncumbrance Cert Unnati.pdf · uploaded 19 Jul 2017Source
Show all 80 documentsShow fewer documents

Migrated

  • 1 Commencement Certificates / NA Order for plotted developmentNere Comencement Certificate.pdf · uploaded 19 Jul 2017Source
  • 1 Declaration in FORM BForm B Builder Nere 01.pdf · uploaded 19 Jul 2017Source
  • 1 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Unnati Architect Certificate 1.pdf · uploaded 19 Jul 2017Source
  • 1 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Unnati Engineer Certificate 01.pdf · uploaded 19 Jul 2017Source
  • 1 Proforma of Allotment letterUNNATI - Flat agreement RERA.pdf · uploaded 19 Jul 2017Source
  • 1 Copy of Layout Approval (in case of layout)Layout Plan 1.pdf · uploaded 20 Jul 2017Source
  • 2 Copy of Layout Approval (in case of layout)Parking Layout 01.pdf · uploaded 20 Jul 2017Source
  • 3 Copy of Layout Approval (in case of layout)3A.pdf · uploaded 20 Jul 2017Source
  • 4 Copy of Layout Approval (in case of layout)4A.pdf · uploaded 20 Jul 2017Source
  • 5 Copy of Layout Approval (in case of layout)6A.pdf · uploaded 20 Jul 2017Source
  • 6 Copy of Layout Approval (in case of layout)7A.pdf · uploaded 20 Jul 2017Source
  • 1 Building Plan Approval (IOD)Layout Plan 1.pdf · uploaded 20 Jul 2017Source
  • 1 Certificates of CA (Form 3)RERA Certificate Sigma Realty01.pdf · uploaded 20 Jul 2017Source
  • 2 Proforma of Allotment letterRERA Aggrement and allotment Letter Unnati.pdf · uploaded 2 Aug 2017Source
  • 2 Details of encumbrancesSigma Realty.pdf · uploaded 30 Nov 2017Source
  • 1 Certificates of CA (Form 5)Form 5 ( UT ) - Sigma Realty.pdf · uploaded 29 Sep 2018Source
  • 2 Certificates of CA (Form 5)Form 5 Sigma Realty.pdf · uploaded 1 Oct 2019Source
  • 1 Architect’s Certificate on Completion of Project (Form 4)Unnati-Phase 01-Form 04.pdf · uploaded 14 Feb 2020Source
  • 1 Details of Restarting of Construction work post lockdownunnati.pdf · uploaded 18 Jun 2020Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 Sigma Realty.pdf · uploaded 13 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Quality Assurance Certificate-Unnati Phase 01.pdf · uploaded 1 Nov 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 - Sigma Realty- 1.pdf · uploaded 12 Mar 2022Source
  • 1 Status of Formation of Legal Entity (Society/Co Op etc.)Society Registration Certificate - Unnati.pdf · uploaded 25 Jan 2023Source
  • 2 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Unnati - Phase I - Q4-2018-19.pdf · uploaded 20 Apr 2023Source
  • 3 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Unnati - Phase I - Q1-2019-2020.pdf · uploaded 24 Apr 2023Source
  • 4 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Unnati - Phase I - Q2-2019-2020.pdf · uploaded 24 Apr 2023Source
  • 5 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Unnati - Phase I - Q3-2019-2020.pdf · uploaded 24 Apr 2023Source
  • 6 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Unnati - Phase I - Q1-2020-2021.pdf · uploaded 24 Apr 2023Source
  • 7 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Unnati - Phase I - Q2-2020-2021.pdf · uploaded 24 Apr 2023Source
  • 8 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Unnati - Phase I - Q3-2020-2021.pdf · uploaded 24 Apr 2023Source
  • 9 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Unnati - Phase I - Q4-2020-2021.pdf · uploaded 24 Apr 2023Source
  • 10 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Unnati - Phase I - Q1-2021-2022.pdf · uploaded 24 Apr 2023Source
  • 11 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Unnati - Phase I - Q2-2021-2022.pdf · uploaded 24 Apr 2023Source
  • 12 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Unnati - Phase I - Q3-2021-2022.pdf · uploaded 24 Apr 2023Source
  • 13 Certificates of Architect (Form 1)(Mandatory for only ongoing project)Form 1 - Unnati - Phase I - Q4-2021-2022.pdf · uploaded 24 Apr 2023Source
  • 2 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Unnati - Phase I - Q4-2018-19.pdf · uploaded 24 Apr 2023Source
  • 3 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Unnati - Phase I - Q1-2019-2020.pdf · uploaded 24 Apr 2023Source
  • 4 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Unnati - Phase I - Q2-2019-2020.pdf · uploaded 24 Apr 2023Source
  • 5 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Unnati - Phase I - Q3-2019-2020.pdf · uploaded 24 Apr 2023Source
  • 6 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Unnati - Phase I - Q1-2020-2021.pdf · uploaded 24 Apr 2023Source
  • 7 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Unnati - Phase I - Q2-2020-2021.pdf · uploaded 24 Apr 2023Source
  • 8 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Unnati - Phase I - Q3-2020-2021.pdf · uploaded 24 Apr 2023Source
  • 9 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Unnati - Phase I - Q4-2020-2021.pdf · uploaded 24 Apr 2023Source
  • 10 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Unnati - Phase I - Q1-2021-2022.pdf · uploaded 24 Apr 2023Source
  • 11 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Unnati - Phase I - Q2-2021-2022.pdf · uploaded 24 Apr 2023Source
  • 12 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Unnati - Phase I - Q3-2021-2022.pdf · uploaded 24 Apr 2023Source
  • 13 Certificates of Engineer (Form 2)(Mandatory for only ongoing project)Form 2 - Unnati - Phase I - Q4-2021-2022.pdf · uploaded 24 Apr 2023Source
  • 2 Certificates of CA (Form 3)Form 3 - Unnati - Phase I - Q4-2018-19.pdf · uploaded 24 Apr 2023Source
  • 3 Certificates of CA (Form 3)Form 3 - Unnati - Phase I - Q1-2019-2020.pdf · uploaded 24 Apr 2023Source
  • 4 Certificates of CA (Form 3)Form 3 - Unnati - Phase I - Q2-2019-2020.pdf · uploaded 24 Apr 2023Source
  • 5 Certificates of CA (Form 3)Form 3 - Unnati - Phase I - Q3-2019-2020.pdf · uploaded 24 Apr 2023Source
  • 6 Certificates of CA (Form 3)Form 3 - Unnati - Phase I - Q1-2020-2021.pdf · uploaded 24 Apr 2023Source
  • 7 Certificates of CA (Form 3)Form 3 - Unnati - Phase I - Q2-2020-2021.pdf · uploaded 24 Apr 2023Source
  • 8 Certificates of CA (Form 3)Form 3 - Unnati - Phase I - Q3-2020-2021.pdf · uploaded 24 Apr 2023Source
  • 9 Certificates of CA (Form 3)Form 3 - Unnati - Phase I - Q4-2020-2021.pdf · uploaded 24 Apr 2023Source
  • 10 Certificates of CA (Form 3)Form 3 - Unnati - Phase I - Q1-2021-2022.pdf · uploaded 24 Apr 2023Source
  • 11 Certificates of CA (Form 3)Form 3 - Unnati - Phase I - Q2-2021-2022.pdf · uploaded 24 Apr 2023Source
  • 12 Certificates of CA (Form 3)Form 3 - Unnati - Phase I - Q3-2021-2022.pdf · uploaded 24 Apr 2023Source
  • 13 Certificates of CA (Form 3)Form 3 - Unnati - Phase I - Q4-2021-2022.pdf · uploaded 24 Apr 2023Source
  • 3 Certificates of CA (Form 5)Form 5 - Unnati Phase I - 2019-2020.pdf · uploaded 24 Apr 2023Source
  • 4 Certificates of CA (Form 5)Form 5 - Unnati Phase I - 2020-2021.pdf · uploaded 24 Apr 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2018-19)Form 5 - Unnati Phase I - 2018-2019.pdf · uploaded 25 Apr 2023Source
  • 1 Declaration about Commencement CertificateUnnati completion -Phase-01_5 flats.pdf · uploaded 21 Oct 2023Source

Technical

  • Document7A.pdf · uploaded 20 Jul 2017Source
  • DocumentLayout Plan 1.pdf · uploaded 20 Jul 2017Source
  • DocumentLayout Plan 1.pdf · uploaded 20 Jul 2017Source
  • DocumentParking Layout 01.pdf · uploaded 20 Jul 2017Source
  • Document3A.pdf · uploaded 20 Jul 2017Source
  • Document4A.pdf · uploaded 20 Jul 2017Source
  • Document6A.pdf · uploaded 20 Jul 2017Source

Technical (Architect)

  • DocumentForm 1 - Unnati - Phase I - Q4-2021-2022.pdf · uploaded 24 Apr 2023Source

Technical (Engineer)

  • DocumentForm 2 - Unnati - Phase I - Q4-2021-2022.pdf · uploaded 24 Apr 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Land & approvals42/2, 42/3

As registered with MahaRERA and published on its project page

Project type
Residential / Group Housing
Status on MahaRERA
Certificate Signed
Unit types
2BHK, 1BHK90 units in all
Address
42/2, 42/3, 42/4PIN 412206
Village
Nere, Mulshi taluka
Designated bank account
51
Developed in phases
Yes

Survey, CTS, gat or plot numbers

42/242/342/4

Boundaries

North
Nere to Punvale 12 Mtrs Existing Road
South
12 Mtrs Proposed Road
East
Survey no 41
West
Survey no 43

Source: registration certificates and MahaRERA's project page, as stated there.

Units & parking90 units

12 of 90 units booked (13%), as the promoter reported to MahaRERA

2BHK · 36 units1BHK · 54 units
BuildingTypeCarpet areaUnitsBooked
A5a62BHK52.14 sq m · 561 sq ft362
B4b5b61BHK33.25 sq m · 358 sq ft5410

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Professionals10

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectAr Kapil Jain—
EngineerM/s. G. A. Bhilare Consultants Pvt. Ltd.—
OtherMohan Vasant Malwadkar—
Registered real estate agentHarleen Realtors—
Registered real estate agentKey2home Property Advisors—
Registered real estate agentLife Space Property Solutions Pvt Ltd—
Registered real estate agentPranoo Realty—
Registered real estate agentRohil Kumar Narayanrao Muley—
Registered real estate agentSuggested Property Private Limited—
Registered real estate agentSunny Bharat Lodha—

Source: MahaRERA project page. Contact details are not shown.

Data through13 Oct 2026SourcesMahaRERA project search · registration certificates · MahaRERA project pageData through is when MahaRERA's project page was last read.Methodology