Siddhivinayak Buildcon
Deedo IDDD-1J75Of 3 registrations whose promised date has arrived, 3 kept it (100%).
Delivery record
1 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vrindavan HeightsP51600019585 | Nashik (M Corp.) | Certificate Signed | 30 Jan 2022 | 30 Jan 2022 | On date |
| Vrindavan ResidencyP51600025209 | Nashik (M Corp.) | Certificate Signed | 30 Dec 2023 | 30 Dec 2023 | On date |
| Vrindavan ParkP51600029679 | Nashik (M Corp.) | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
| Vrindavan PrideP51600080285 | Nashik (M Corp.) | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Siddhivinayak Buildcon, in questions
Does Siddhivinayak Buildcon finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Siddhivinayak Buildcon registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.
Does Siddhivinayak Buildcon have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.