Siddhidata Developers
Deedo IDDD-NR5YOf 3 registrations whose promised date has arrived, 3 kept it (100%).
Delivery record
None of 3 registrations with dates has moved or missed its RERA date
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Illona ResidencyP52100021916 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 30 Dec 2021 | 30 Dec 2021 | On date |
| Innara ResidencyP52100029850 | Wakad | Certificate Signed | 31 Dec 2022 | 31 Dec 2022 | On date |
| Shreetej ResidencyP52100046521 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | On date |
Siddhidata Developers, in questions
Does Siddhidata Developers finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Siddhidata Developers registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.
Does Siddhidata Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.