Shubhashree Infrastructure
Deedo IDDD-58FDOf 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 22 mo late.
Delivery record
1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shubhashree PrideP52700014996 | Karad (M Cl) | Certificate Signed | 30 Sep 2018 | 30 Sep 2018 | On date |
| Shubhashree PrasadP52700018770 | Karad (M Cl) | Certificate Signed | 30 Oct 2022 | 30 Oct 2022 | On date |
| Shubhashree IconP52700050500 | Malkapur (Np) | Certificate Signed | 5 Jan 2025 | 5 Jan 2025 | +22 mo* |
Shubhashree Infrastructure, in questions
Does Shubhashree Infrastructure finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 22 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shubhashree Infrastructure registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does Shubhashree Infrastructure have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.