Shubhada Co Op Hsg Soc Limited

Deedo IDDD-QMGD

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay8 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shubhada Co-Operative Housing Society LtdP51700051508DombivliCertificate Signed31 Mar 202631 Jul 2026+8 mo*

Shubhada Co Op Hsg Soc Limited, in questions

Does Shubhada Co Op Hsg Soc Limited finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shubhada Co Op Hsg Soc Limited registered with MahaRERA?

1 project under 1 MahaRERA registration; 0 completed on MahaRERA.

Does Shubhada Co Op Hsg Soc Limited have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology