Shrushti Developers
Company or firm · 6 projects · 6 MahaRERA registrations
Projects66 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%4 of 4 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| EleganceP99000014549 | Palghar | 2017 | Not reported | 30 Dec 2021 | — | On date |
| ClassiqueP99000014864 | Palghar | 2018 | Not reported | 30 Dec 2022 | — | On date |
| Shubh-AanganP99000016774 | Palghar | 2018 | Not reported | 30 Dec 2020 | — | On date |
| EliteP99000035038 | Palghar | 2022 | Not reported | 31 Dec 2024 | — | On date |
| Bafna LuxuriaP99000050574 | Mahim | 2023 | Not reported | 31 Dec 2026 | — | On date |
| SierraPM1240002601325 | Tembhode | 2026 | Not reported | 31 Dec 2030 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 4 of 4 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
