Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late — the same as Maharashtra's 4 mo.

Projects99 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

6 of 9 registrations with dates moved or missed their RERA date · months late against the original promise

9 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shreeji AspireP51800003919BorivaliCertificate Signed30 Nov 202028 Nov 2022+24 mo
Shreeji Atlantis Wing AP51800004400BorivaliCertificate Signed31 Dec 202331 Dec 2023On date
Shreeji Atlantis Wing BP51800047335BorivaliCertificate Signed31 Dec 202731 Dec 2027On date
Shreeji Eternity Wing - DP51800054233ValnaiCertificate Signed30 Jun 202830 Oct 2028+4 mo
Shreeji Eternity Wing - A, Shreeji Eternity Wing - B, Shreeji Eternity Wing - CP51800054310ValnaiActive30 Jun 2027—On date
Shreeji BlissP51800076989ValnaiCertificate Signed31 Jan 202831 May 2028+4 mo
Shreeji NakshtraP51800079261ValnaiCertificate Signed31 Aug 202831 Dec 2028+4 mo
Shreeji TrinityPM1180002502235ValnaiCertificate Signed30 Jun 203030 Oct 2030+4 mo
Shreeji AmberPM1180002601053ValnaiCertificate Signed30 Jun 203030 Oct 2030+4 mo

Shreeji Construction, in questions

Does Shreeji Construction finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shreeji Construction registered with MahaRERA?

9 projects under 9 MahaRERA registrations; 2 completed on MahaRERA.

Does Shreeji Construction have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology