Deedo IDDD-5XKDOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 42 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Siddheshwar Infraventures Private LimitedP50500025408 | Wela Harichandra | Certificate Signed | 30 Nov 2022 | 30 Nov 2023 | +48 mo* |
| Shree Siddheshwar Nagar 2P50500029571 | Nagpur (M Corp.) | Certificate Signed | 31 Mar 2025 | 31 Mar 2028 | +36 mo |
Shree Siddheshwar Infraventures Pvt Ltd, in questions
Does Shree Siddheshwar Infraventures Pvt Ltd finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 42 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shree Siddheshwar Infraventures Pvt Ltd registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Shree Siddheshwar Infraventures Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.