Company or firm · first RERA registration 2020

Shree Siddheshwar Infraventures Pvt Ltd

Deedo IDDD-5XKD

Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 42 mo late.

Projects22 RERA registrations
Kept RERA date0%Maharashtra: 73%
Median delay42 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Shree Siddheshwar Infraventures Private LimitedP50500025408Wela HarichandraCertificate Signed30 Nov 202230 Nov 2023+48 mo*
Shree Siddheshwar Nagar 2P50500029571Nagpur (M Corp.)Certificate Signed31 Mar 202531 Mar 2028+36 mo

Shree Siddheshwar Infraventures Pvt Ltd, in questions

Does Shree Siddheshwar Infraventures Pvt Ltd finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 42 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shree Siddheshwar Infraventures Pvt Ltd registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.

Does Shree Siddheshwar Infraventures Pvt Ltd have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology