Shree Sai Developers
Deedo IDDD-WNV8Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 17 mo late.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sai VishwaP52100013146 | Undri | Certificate Signed | 30 Dec 2021 | 31 Dec 2024 | +59 mo* |
| Sai Vishwa A WingP52100028279 | Undri | Certificate Signed | 30 Jun 2025 | 30 Jun 2025 | +17 mo* |
| Savvitri AarcadeP52100079994 | Pisoli | Active | 31 Dec 2028 | 30 Apr 2029 | +4 mo |
Shree Sai Developers, in questions
Does Shree Sai Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 17 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shree Sai Developers registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 0 completed on MahaRERA.
Does Shree Sai Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.