Shree Neelkamal Housing & Infrastructure
Deedo IDDD-7D0YOf 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late.
Delivery record
4 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Neelkamal SaritaP51600045682 | Talegaon(Dindori) | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | +11 mo* |
| Neelkamal SaritaP51600046001 | Talegaon(Dindori) | Certificate Signed | 31 Dec 2025 | 31 Dec 2029 | +48 mo |
| Neelkamal SaritaP51600049056 | Talegaon(Dindori) | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
| Neelkamal SaritaP51600054554 | Talegaon(Dindori) | Certificate Signed | 31 Dec 2026 | 30 Apr 2027 | +4 mo |
Shree Neelkamal Housing & Infrastructure, in questions
Does Shree Neelkamal Housing & Infrastructure finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shree Neelkamal Housing & Infrastructure registered with MahaRERA?
1 project under 4 MahaRERA registrations; 0 completed on MahaRERA.
Does Shree Neelkamal Housing & Infrastructure have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.