Neelkamal Sarita

Completion due Dec 2029

Talegaon(Dindori), Nashik 422202 |Promoter: Shree Neelkamal Housing & Infrastructure

6 Jun 2022Registered with MahaRERAFirst of 4 registrations
31 Dec 2026Promised completionLatest across registrations
31 Dec 2029Revised completion1 of 4 registrations pushed back, by up to 4 years
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA

RERA registrations
4
Phases
4

Location

Coordinates as published by MahaRERA

View on OpenStreetMap 20.14613, 73.81943
Neelkamal Sarita is at latitude 20.14613, longitude 73.81943.

Also registered as

Neelkamal Sarita Phase 1Neelkamal Sarita Phase 2Neelkamal Sarita Phase 4Neelkamal Sarita Phase 3
MahaRERA's project page hasn't been imported for this project yet.

Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).

Latest registered deals

No registered transactions matched to this project yetSales, resales and rentals appear here once registered documents from authorised IGR feeds are matched to this project.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion promised for 31 Dec 2025

P51600045682

The latest completion date on record passed 10 months ago.

Registered
6 Jun 2022
Promised
31 Dec 2025

Completion pushed back 4 years

P51600046001
Registered
15 Jun 2022
Promised
31 Dec 2025
Revised
31 Dec 2029

Completion promised for 31 Dec 2026

P51600049056
Registered
30 Jan 2023
Promised
31 Dec 2026

Completion promised for 31 Dec 2026

P51600054554
Registered
31 Jan 2024
Promised
31 Dec 2026

4 RERA registrations

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P516000456826 Jun 202231 Dec 2025—Shree Neelkamal Housing & InfrastructureProject page
P5160004600115 Jun 202231 Dec 202531 Dec 2029Shree Neelkamal Housing & InfrastructureProject page
P5160004905630 Jan 202331 Dec 2026—Shree Neelkamal Housing & InfrastructureProject page
P5160005455431 Jan 202431 Dec 2026—Shree Neelkamal Housing & InfrastructureProject page

Documents

5 documents held by Deedo

Registration certificates

  • Registration certificateP51600049056 · 30 Jan 2023ViewSource
  • Registration certificateP51600045682 · 25 Nov 2024ViewSource
  • Registration certificateP51600046001 · 21 Dec 2024ViewSource
  • Registration certificateP51600054554 · 17 Sep 2026ViewSource

Extension certificate

  • Extension certificateP51600046001 · 13 Jan 2026ViewSource

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Talegaon(Dindori)

Survey, CTS, gat or plot numbers

9/2Amenity Space of Gut No. 8/1Part of Gut No. 8/1

Source: registration certificates, as stated there.

SourcesMahaRERA project search · registration certificatesMethodology