Shree Krishna Sai Development Corporation

Company or firm · 7 projects · 7 MahaRERA registrations

Projects77 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%1 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Sai IconicP51800002150Andheri2017Not reported31 Mar 2019—On date
Khandelwal Luxor Wing BP51800045675Borivali2022Not reported31 Dec 2027—On date
Khandelwal Reserve Wing BP51800045778Borivali2022Not reported31 Dec 2027—On date
Khandelwal Luxor Wing AP51800077617Gorai2024Not reported31 Dec 2029—On date
Khandelwal Reserve Wing AP51800077860Gorai2024Not reported31 Dec 2029—On date
Khandelwal TattvaPM1180002501779Ambivali2025Not reported31 Dec 2030—On date
Khandelwal AcropolisPM1180002502160Ambivali2026Not reported31 Dec 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Sai IconicOn date
  • Khandelwal Luxor Wing BOn date
  • Khandelwal Reserve Wing BOn date
  • Khandelwal Luxor Wing AOn date
  • Khandelwal Reserve Wing AOn date
  • Khandelwal TattvaOn date
  • Khandelwal AcropolisOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology