Shree Krishna Sai Development Corporation
Company or firm · 7 projects · 7 MahaRERA registrations
Projects77 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%1 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Sai IconicP51800002150 | Andheri | 2017 | Not reported | 31 Mar 2019 | — | On date |
| Khandelwal Luxor Wing BP51800045675 | Borivali | 2022 | Not reported | 31 Dec 2027 | — | On date |
| Khandelwal Reserve Wing BP51800045778 | Borivali | 2022 | Not reported | 31 Dec 2027 | — | On date |
| Khandelwal Luxor Wing AP51800077617 | Gorai | 2024 | Not reported | 31 Dec 2029 | — | On date |
| Khandelwal Reserve Wing AP51800077860 | Gorai | 2024 | Not reported | 31 Dec 2029 | — | On date |
| Khandelwal TattvaPM1180002501779 | Ambivali | 2025 | Not reported | 31 Dec 2030 | — | On date |
| Khandelwal AcropolisPM1180002502160 | Ambivali | 2026 | Not reported | 31 Dec 2030 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology