Skip to content
Deedo home
Menu

Shree Datta Developers

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%1 of 1 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Barku BhoomiP51700019020Tisgaon2018Not reported30 Dec 2024—On date
Barku HeightP51700049873Kalyan2023Not reported31 Dec 2026—On date
Barku HorizonPR1330002501759Kalyan2025Not reported31 Dec 2030—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Barku BhoomiOn date
  • Barku HeightOn date
  • Barku HorizonOn date

Track record notes

  • 1 of 1 registration whose RERA proposed completion date has passed was never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology