Company or firm · first RERA registration 2017

Shree Construction & Developers

Deedo IDDD-HDM8

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 41 mo late.

Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay41 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Nakshtra BungalowsP53000003726Vadgaon Kasba (M Cl)Certificate Signed1 Aug 20181 Aug 2018On date
Ayodhya ParkP53000025561Vadgaon Kasba (M Cl)Certificate Signed30 Jun 202330 Jun 2023+41 mo*
Thorat HeightsP53000051245Vadgaon Kasba (M Cl)Certificate Signed31 Dec 202731 Dec 2027On date

Shree Construction & Developers, in questions

Does Shree Construction & Developers finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 41 mo late. Across Maharashtra, 73% kept their date.

How many projects has Shree Construction & Developers registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Shree Construction & Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology