Shree Construction & Developers
Deedo IDDD-HDM8Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 41 mo late.
Delivery record
1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nakshtra BungalowsP53000003726 | Vadgaon Kasba (M Cl) | Certificate Signed | 1 Aug 2018 | 1 Aug 2018 | On date |
| Ayodhya ParkP53000025561 | Vadgaon Kasba (M Cl) | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | +41 mo* |
| Thorat HeightsP53000051245 | Vadgaon Kasba (M Cl) | Certificate Signed | 31 Dec 2027 | 31 Dec 2027 | On date |
Shree Construction & Developers, in questions
Does Shree Construction & Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 41 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shree Construction & Developers registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does Shree Construction & Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.