Skip to content
Deedo home
Menu

Shree Chaitanya Developers

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Ishan EnclaveP52700014534Karanje Tarf Satara (Ct)2017Not reported30 Dec 2021—On date
Piyush KunjP52700027013Kodoli (Ct)2020Not reported30 Jun 2024—On date
Prajakta PushpP52700027383Kodoli (Ct)2020Not reported30 Jun 2024—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Ishan EnclaveOn date
  • Piyush KunjOn date
  • Prajakta PushpOn date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology