Shree Balaji Associates Pune Llp
Deedo IDDD-5Z7VOf 5 registrations whose promised date has arrived, 2 kept it (40%). The rest ran a median 4 mo late.
Delivery record
7 of 10 registrations with dates moved or missed their RERA date · months late against the original promise
10 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
| Case | Project | Date |
|---|---|---|
| Deregistered | Ganga Capital SquareDeregistered: Ganga Capital Square | Not on record |
| complaint | GANGA NEWTOWN PH 3 C BldgComplaint CC12504304 | Not on record |
| complaint | GANGA NEWTOWN PH 3 C BldgComplaint CC12606139 | Not on record |
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Ganga NewtownP52100001431 | Dhanori | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Ganga Newtown Ph 02P52100019275 | Pune (M Corp.) | Lapsed | 30 Dec 2025 | 30 Dec 2025 | +11 mo* |
| Ganga Capital SquareP52100019299 | Vadgaonsheri | Certificate Signed | 30 Dec 2024 | 30 Dec 2024 | +23 mo* |
| Ganga PlatinumP52100031418 | Kharadi | Certificate Signed | 31 Oct 2026 | 31 Oct 2026 | +1 mo* |
| GANGA NEWTOWN PH 3 C BldgP52100034400 | Dhanori | Completed | 30 Jun 2026 | 30 Jun 2026 | On date |
| Ganga PlatinumP52100054598 | Kharadi | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
| Ganga NewtownP52100055461 | Dhanori | Certificate Signed | 30 Jun 2027 | 31 Dec 2027 | +6 mo |
| Ganga NewtownP52100079278 | Dhanori | Certificate Signed | 30 Jun 2028 | 30 Oct 2028 | +4 mo |
| Ganga Capitol OneP52100080094 | Keshavnagarmundwa | Certificate Signed | 31 Dec 2029 | 30 Apr 2030 | +4 mo |
| Ganga NewtownPM1260002601659 | Dhanori | Certificate Signed | 31 Dec 2030 | 31 Dec 2030 | On date |
Shree Balaji Associates Pune Llp, in questions
Does Shree Balaji Associates Pune Llp finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 2 kept it (40%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shree Balaji Associates Pune Llp registered with MahaRERA?
7 projects under 10 MahaRERA registrations; 2 completed on MahaRERA.
Does Shree Balaji Associates Pune Llp have MahaRERA regulatory cases?
3 regulatory cases name its registrations.