Deedo IDDD-MQCGOf 4 registrations whose promised date has arrived, 3 kept it (75%). The rest ran a median 24 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shree Amba Business ParkP50300015750 | Amravati (M Corp.) | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 mo |
| Shree Amba Business ParkP50300016859 | Amravati (M Corp.) | Lapsed | 30 Sep 2020 | — | On date |
| Shree Amba Business ParkP50300019011 | Amravati (M Corp.) | Completed | 30 Dec 2022 | — | On date |
| Shree Amba Business ParkP50300023525 | Amravati (M Corp.) | Completed | 30 Mar 2023 | — | On date |
Shree Amba Business Park, in questions
Does Shree Amba Business Park finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 3 kept it (75%). The rest ran a median 24 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shree Amba Business Park registered with MahaRERA?
1 project under 4 MahaRERA registrations; 4 completed on MahaRERA.
Does Shree Amba Business Park have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.