Deedo IDDD-PA3JOf 3 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 25 mo late.
Delivery record
3 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| 19 Grand WestP52100017919 | Thergaon | Certificate Signed | 30 Nov 2022 | 30 Dec 2024 | +25 mo |
| 19 Grand WestP52100018030 | Thergaon | Certificate Signed | 30 Nov 2022 | 30 Dec 2024 | +48 mo* |
| 19 GRAND WEST - C WING and D WINGP52100031024 | Thergaon | Certificate Signed | 31 Dec 2024 | 31 Dec 2024 | +23 mo* |
Shivam Development Ventures Llp, in questions
Does Shivam Development Ventures Llp finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 25 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shivam Development Ventures Llp registered with MahaRERA?
2 projects under 3 MahaRERA registrations; 1 completed on MahaRERA.
Does Shivam Development Ventures Llp have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.