Shivam Construction
Company or firm · 3 projects · 3 MahaRERA registrations
Also appears as M/S SHIVAM CONSTRUCTION
Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shivam PalaceP52000015309 | Neral | 2018 | Not reported | 31 Dec 2019 | — | On date |
| Matru ChhayaP52000024823 | Mamdapur | 2020 | Not reported | 30 Dec 2022 | — | On date |
| Unity HomesP52000050427 | Mamdapur | 2023 | Not reported | 31 Dec 2025 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
- MahaRERA records spell this promoter's name 2 ways; all of them are linked to this page through its registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology