Shinde And Associates
Deedo IDDD-FJMCOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 47 mo late.
Delivery record
1 of 1 registration with dates moved or missed their RERA date · months late against the original promise
1 registration with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Shiv-Rudra EmporiumP53100021052 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 30 Dec 2022 | 30 Dec 2022 | +47 mo* |
Shinde And Associates, in questions
Does Shinde And Associates finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 47 mo late. Across Maharashtra, 73% kept their date.
How many projects has Shinde And Associates registered with MahaRERA?
1 project under 1 MahaRERA registration; 0 completed on MahaRERA.
Does Shinde And Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.