Shilp Constructions
Deedo IDDD-277XOf 4 registrations whose promised date has arrived, 4 kept it (100%).
Delivery record
1 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Aanand Shilp ApartmentP51500001870 | Aurangabad | Certificate Signed | 31 Dec 2018 | 31 Dec 2018 | On date |
| Viraj Shilp ResidencyP51500024691 | Aurangabad (M Corp.) | Completed | 1 Jan 2023 | — | On date |
| Sai Shilp ResidencyP51500031353 | Aurangabad (M Corp.) | Certificate Signed | 1 Apr 2023 | 1 Apr 2023 | On date |
| Pushp Nagari Phase 1P51500048980 | Ghanegaon | Certificate Signed | 1 Dec 2024 | 1 Dec 2024 | On date |
| Shilp Gaurav HeightsP51500079845 | Garkheda | Certificate Signed | 31 Dec 2027 | 30 Apr 2028 | +4 mo |
Shilp Constructions, in questions
Does Shilp Constructions finish projects on time?
Of 4 MahaRERA registrations whose promised completion date has arrived, 4 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Shilp Constructions registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 4 completed on MahaRERA.
Does Shilp Constructions have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.