Sheth Developers Private Limited
Deedo IDDD-30ZDOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 29 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Vasant FionaP51700000734 | Thane (M Corp.) | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| ClarionP51800001685 | Borivali | Certificate Signed | 30 Jun 2019 | 28 Nov 2021 | +29 mo |
Sheth Developers Private Limited, in questions
Does Sheth Developers Private Limited finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 29 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sheth Developers Private Limited registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Sheth Developers Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.