Sharif Hasan Jahangir Dalwai
Deedo IDDD-RHHEOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Mannat TowerP52800032648 | Mirjoli | Certificate Signed | 30 Nov 2025 | 30 Nov 2025 | +12 mo* |
| Malik Hills Wing A And BP52800077482 | Uktad | Certificate Signed | 31 May 2029 | 30 Sep 2029 | +4 mo |
Sharif Hasan Jahangir Dalwai, in questions
Does Sharif Hasan Jahangir Dalwai finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sharif Hasan Jahangir Dalwai registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Sharif Hasan Jahangir Dalwai have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.