Serene Lifespaces
Deedo IDDD-DT1WOf 5 registrations whose promised date has arrived, 5 kept it (100%).
Delivery record
None of 5 registrations with dates has moved or missed its RERA date
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| GulmoharP52000000719 | Ulawe | Certificate Signed | 1 Jun 2019 | 1 Jun 2019 | On date |
| SunflowerP52000000930 | Ulawe | Certificate Signed | 30 Jun 2019 | 30 Jun 2019 | On date |
| LotusP52000002500 | Ulawe | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| TulipsP52000023409 | Ulawe | Certificate Signed | 30 Sep 2023 | 30 Sep 2023 | On date |
| OrchidsP52000051070 | Ulawe | Certificate Signed | 31 Dec 2025 | 31 Dec 2025 | On date |
Serene Lifespaces, in questions
Does Serene Lifespaces finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 5 kept it (100%). Across Maharashtra, 73% kept their date.
How many projects has Serene Lifespaces registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 5 completed on MahaRERA.
Does Serene Lifespaces have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.