Sarovar Associates

Company or firm · 1 project · 2 MahaRERA registrations

1Projects2 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+11 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Abhilasha ParkP52100009755Dehu2017Certificate Signed31 Dec 201931 Dec 2019On date
Abhilasha ParkP52100023526Dehu2019Certificate Signed31 Jul 202330 Apr 2025+21 months

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Abhilasha ParkOn date
  • Abhilasha Park+21 mo

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 21 months, for Abhilasha Park (P52100023526).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology