Sarovar Associates
Deedo IDDD-Q3NDOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 21 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Abhilasha ParkP52100009755 | Dehu | Certificate Signed | 31 Dec 2019 | 31 Dec 2019 | On date |
| Abhilasha ParkP52100023526 | Dehu | Certificate Signed | 31 Jul 2023 | 30 Apr 2025 | +21 mo |
Sarovar Associates, in questions
Does Sarovar Associates finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 21 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sarovar Associates registered with MahaRERA?
1 project under 2 MahaRERA registrations; 2 completed on MahaRERA.
Does Sarovar Associates have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.