Individual promoter · first RERA registration 2017

Saroj Shrawankumar Bagaria

Deedo IDDD-465F

Of 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 48 mo late — longer than Maharashtra's 4 mo.

Projects11 RERA registration
Kept RERA date0%Maharashtra: 73%
Median delay48 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 1 registration with dates moved or missed their RERA date · months late against the original promise

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Rahul ExcellenceP51700012698AmbarnathCertificate Signed31 Dec 201830 Dec 2022+48 mo

Saroj Shrawankumar Bagaria, in questions

Does Saroj Shrawankumar Bagaria finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 48 mo late. Across Maharashtra, 73% kept their date.

How many projects has Saroj Shrawankumar Bagaria registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Saroj Shrawankumar Bagaria have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology