Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 8 mo late.

Projects22 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay8 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise

2 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Saras NestP52000026901UlaweCertificate Signed30 Sep 202430 Sep 2024On date
Saras CasaP52000051264UlaweCertificate Signed31 Mar 202631 Jul 2026+8 mo*

Saras Group, in questions

Does Saras Group finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.

How many projects has Saras Group registered with MahaRERA?

2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.

Does Saras Group have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.