Sara Towers Pvt Ltd
Deedo IDDD-PZSWOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 8 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sara Venkatesh F Type BuildingP51500032237 | Wadgaon Kolhati (Ct) | Completed | 31 Mar 2023 | 30 Mar 2024 | +12 mo |
| Sara Business HubP52100048684 | Kharabwadi (Ct) | Certificate Signed | 31 Mar 2027 | 31 Jul 2027 | +4 mo |
Sara Towers Pvt Ltd, in questions
Does Sara Towers Pvt Ltd finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 8 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sara Towers Pvt Ltd registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Sara Towers Pvt Ltd have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.