Deedo IDDD-QX64Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 4 mo late.
Delivery record
3 of 4 registrations with dates moved or missed their RERA date · months late against the original promise
4 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Emmanuel SpacesP53100012428 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 15 Dec 2018 | 15 Dec 2018 | On date |
| Emmanuel EnclaveP53100028320 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 15 Jun 2024 | 15 Jun 2024 | +29 mo* |
| Emmanuel IconP53100078156 | Sangli Miraj Kupwad (M Corp.) | Certificate Signed | 29 Oct 2027 | 29 Feb 2028 | +4 mo |
| Emmanuel CornerstoneP53000081072 | Ichalkaranji (M Cl) | Certificate Signed | 31 Oct 2032 | 28 Feb 2033 | +4 mo |
Santosh Mohan Arawattigi, in questions
Does Santosh Mohan Arawattigi finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 4 mo late. Across Maharashtra, 73% kept their date.
How many projects has Santosh Mohan Arawattigi registered with MahaRERA?
4 projects under 4 MahaRERA registrations; 1 completed on MahaRERA.
Does Santosh Mohan Arawattigi have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.