Company or firm · first RERA registration 2019

Sankalp Builders And Developers

Deedo IDDD-MNVQ

Of 3 registrations whose promised date has arrived, 3 kept it (100%).

Projects33 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 3 registrations with dates has moved or missed its RERA date

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sankalp HeritageP50300019113Nandgaon PethCompleted28 Nov 2021—On date
Sankalp HeavenP50300029249Amravati (M Corp.)Certificate Signed31 May 202431 May 2024On date
Sankalp PrideP50300051398Amravati (M Corp.)Completed31 Mar 2026—On date

Sankalp Builders And Developers, in questions

Does Sankalp Builders And Developers finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 3 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Sankalp Builders And Developers registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.

Does Sankalp Builders And Developers have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology