Skip to content
Deedo home
Menu

Sanjay Manmode And Mohan Manmode

Company or firm · 3 projects · 3 MahaRERA registrations

Projects33 RERA registrations
Completed0as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Manmode Town Unit 2P50400045567Wardha2022Not reported31 Mar 2025—On date
Manmode Town Unit 3P50400045572Wardha2022Not reported31 Mar 2025—On date
Manmode Town Unit 1P50400045574Pipri (Ct)2022Not reported31 Mar 2025—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Manmode Town Unit 2On date
  • Manmode Town Unit 3On date
  • Manmode Town Unit 1On date

Track record notes

  • 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology