Skip to content
Individual promoter · first RERA registration 2017

Sandip Shivajirao Jadhav Huf

Deedo IDDD-6NAD

Of 1 registration whose promised date has arrived, 1 kept it (100%).

Projects11 RERA registration
Kept RERA date100%Maharashtra: 73%
Median delay0 monone ran late
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

None of 1 registration with dates has moved or missed its RERA date

1 registration with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Pushp Kunj ResidencyP52700013223Kodoli (Ct)Certificate Signed20 Jul 201820 Jul 2018On date

Sandip Shivajirao Jadhav Huf, in questions

Does Sandip Shivajirao Jadhav Huf finish projects on time?

Of 1 MahaRERA registration whose promised completion date has arrived, 1 kept it (100%). Across Maharashtra, 73% kept their date.

How many projects has Sandip Shivajirao Jadhav Huf registered with MahaRERA?

1 project under 1 MahaRERA registration; 1 completed on MahaRERA.

Does Sandip Shivajirao Jadhav Huf have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology