Individual promoter · first RERA registration 2017

Samir Shrinivas Kale

Deedo IDDD-YJJH

Of 32 registrations whose promised date has arrived, 29 kept it (91%). The rest ran a median 7 mo late.

Projects3138 RERA registrations
Kept RERA date91%Maharashtra: 73%
Median delay7 mowhen late
First sales on record0registered first-sale deeds matched so far
Regulatory cases1no insolvency

Delivery record

6 of 38 registrations with dates moved or missed their RERA date · months late against the original promise

Show all 38 registrations

38 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Mango Holiday Village, Guhagar - Phase 4P52800003399Kirtanwadi Tarf GuhagarCertificate Signed31 Jan 202030 Jan 2021+12 mo
Mango HeritageP52800006761GuhagarCertificate Signed31 Mar 201831 Mar 2019+12 mo
Sunset Holiday ApartmentsP52800020417GuhagarCertificate Signed5 Jan 20245 Jan 2024On date
Mango Holiday Village Guhagar Bungalow No 42 and 93P52800020526Kirtanwadi Tarf GuhagarCertificate Signed3 Apr 20223 Apr 2022On date
Mango Holiday Village, Guhagar - Bungalow No 54P52800021888Kirtanwadi Tarf GuhagarCertificate Signed1 Aug 20221 Aug 2022On date
Mango Holiday Village, Guhagar - Bungalow No 6P52800024075Kirtanwadi Tarf GuhagarCertificate Signed30 Dec 202230 Dec 2022On date
Pranav EnclaveP51700024548Thane (M Corp.)Certificate Signed30 Mar 202430 Mar 2024On date
Mango Holiday Village, Guhagar - Bungalow No 103P52800026667Kirtanwadi Tarf GuhagarCertificate Signed30 Jun 202230 Jun 2022On date
Mango Holiday Village Guhagar BungalowP52800028056Kirtanwadi Tarf GuhagarCertificate Signed30 Nov 202230 Nov 2022On date
Mango Holiday Village Guhagar BungalowP52800028581Kirtanwadi Tarf GuhagarCertificate Signed30 Jun 202330 Jun 2023On date
Mango Holiday Village Guhagar BungalowP52800028597Kirtanwadi Tarf GuhagarCertificate Signed30 Jun 202330 Jun 2023On date
Mango Holiday Village Guhagar - Bungalow No 99P52800029127Kirtanwadi Tarf GuhagarCertificate Signed31 Dec 202231 Dec 2022On date
Mango Holiday Village Guhagar - Bungalow No 41P52800029170Kirtanwadi Tarf GuhagarCertificate Signed31 Dec 202231 Dec 2022On date
Mango Holiday Village Guhagar - Bungalow No 97P52800029172Kirtanwadi Tarf GuhagarCertificate Signed31 Dec 202231 Dec 2022On date
Mango Holiday Village Guhagar - Bungalow No 102P52800030532Kirtanwadi Tarf GuhagarCertificate Signed31 May 202331 May 2023On date
Mango Holiday Village Guhagar - Bungalow No 27P52800031199Kirtanwadi Tarf GuhagarCertificate Signed1 Oct 20231 Oct 2023On date
Mango Holiday Village Guhagar - Bungalow No 94P52800032054Kirtanwadi Tarf GuhagarCertificate Signed1 Nov 20231 Nov 2023On date
Mango Holiday Village Guhagar Bungalow No 95P52800032945Kirtanwadi Tarf GuhagarCertificate Signed1 Nov 20231 Nov 2023On date
Mango Holiday Village Guhagar Bungalow No 96P52800033522Kirtanwadi Tarf GuhagarCertificate Signed31 Mar 202431 Mar 2024On date
Mango Holiday Village Guhagar Bungalow No 88P52800033586Kirtanwadi Tarf GuhagarCertificate Signed31 Mar 202431 Mar 2024On date
Mango Holiday Village Guhagar Bungalow No 100P52800034054Kirtanwadi Tarf GuhagarCertificate Signed31 Mar 202431 Mar 2024On date
Mango Holiday Village Guhagar Bungalow No 106P52800034745Kirtanwadi Tarf GuhagarCertificate Signed31 Mar 202431 Mar 2024On date
Mango Holiday Village Guhagar Bungalow No 87P52800045443Kirtanwadi Tarf GuhagarCertificate Signed31 May 202431 May 2024On date
Harikunj EnclaveP51700047799Thane (M Corp.)Certificate Signed31 Aug 202531 Aug 2025On date
Mango Holiday Village Guhagar Bungalow No 56P52800049406Kirtanwadi Tarf GuhagarCertificate Signed31 Dec 202431 Dec 2024On date
Mango Holiday Village Guhagar Bungalow No 92P52800050804Kirtanwadi Tarf GuhagarCertificate Signed30 Sep 202530 Sep 2025On date
Mango Holiday Village Guhagar Bungalow No 108P52800051905Kirtanwadi Tarf GuhagarCertificate Signed31 Dec 202531 Dec 2025On date
Mango Holiday Village Guhagar Bungalow No 90P52800051906Kirtanwadi Tarf GuhagarCertificate Signed30 Nov 202530 Nov 2025On date
Mango Holiday Village Guhagar BungalowP52800052799Kirtanwadi Tarf GuhagarCertificate Signed31 Jan 202631 Jan 2026+10 mo*
Mango Holiday Village Guhagar BungalowP52800052815Kirtanwadi Tarf GuhagarCertificate Signed28 Feb 202628 Feb 2026On date
Mango Lakeview GuhagarP52800054932GuhagarCertificate Signed30 Sep 202930 Jan 2030+4 mo
Mango Holiday Village Guhagar BungalowP52800056232Kirtanwadi Tarf GuhagarCertificate Signed31 Aug 202631 Aug 2026On date
Mango Holiday Village Guhagar BungalowP52800066569Kirtanwadi Tarf GuhagarCertificate Signed15 Oct 202615 Oct 2026On date
Mango Lakefront Paradise Guhagar Bungalow No 38P52800077206Kondwadi Tarfe PatpanhaleCertificate Signed30 Nov 202630 Mar 2027+4 mo
MHVG BungalowP52800079596Kirtanwadi Tarf GuhagarCertificate Signed31 Aug 202731 Aug 2027On date
MHVG BungalowP52800079665Kirtanwadi Tarf GuhagarCertificate Signed30 Jun 202730 Jun 2027On date
MHVG BungalowP52800079696Kirtanwadi Tarf GuhagarCertificate Signed30 Sep 202730 Sep 2027On date
Mango Lakefront Paradise GuhagarP52800080958Kondwadi Tarfe PatpanhaleCertificate Signed28 Feb 203528 Jun 2035+4 mo
Show all 38 registrationsShow fewer

Samir Shrinivas Kale, in questions

Does Samir Shrinivas Kale finish projects on time?

Of 32 MahaRERA registrations whose promised completion date has arrived, 29 kept it (91%). The rest ran a median 7 mo late. Across Maharashtra, 73% kept their date.

How many projects has Samir Shrinivas Kale registered with MahaRERA?

31 projects under 38 MahaRERA registrations; 34 completed on MahaRERA.

Does Samir Shrinivas Kale have MahaRERA regulatory cases?

1 regulatory case name its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology