Sairaj Enterprises

Deedo IDDD-Y7EG

Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 7 mo late — longer than Maharashtra's 4 mo.

Projects33 RERA registrations
Kept RERA date50%Maharashtra: 73%
Median delay7 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise

3 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Sai PoojaP51700045755BadlapurCertificate Signed31 Dec 202431 Dec 2024On date
Sairaj EmeraldP51700049097Badlapur (M Cl)Certificate Signed25 Sep 202323 Jul 2024+10 mo
Sai Hillcrest Wing A & BP51700079190BelavliCertificate Signed30 Sep 202930 Jan 2030+4 mo

Sairaj Enterprises, in questions

Does Sairaj Enterprises finish projects on time?

Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 7 mo late. Across Maharashtra, 73% kept their date.

How many projects has Sairaj Enterprises registered with MahaRERA?

3 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.

Does Sairaj Enterprises have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.