Deedo IDDD-YKD4Of 5 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 12 mo late.
Delivery record
5 of 5 registrations with dates moved or missed their RERA date · months late against the original promise
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sairaj HeightsP52100001542 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Sais LeelaP52100001705 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| Sai Exotique D WingP52100004171 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 31 Aug 2019 | 28 Aug 2022 | +36 mo |
| Sai Exotique B WingP52100009721 | Pimpri Chinchawad (M Corp.) | Certificate Signed | 31 Dec 2018 | 31 Dec 2019 | +12 mo |
| ShantivanP52100032130 | Pimpri | Certificate Signed | 10 Aug 2026 | 10 Aug 2026 | +3 mo* |
Saibaba Sales Private Limited, in questions
Does Saibaba Sales Private Limited finish projects on time?
Of 5 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 12 mo late. Across Maharashtra, 73% kept their date.
How many projects has Saibaba Sales Private Limited registered with MahaRERA?
5 projects under 5 MahaRERA registrations; 4 completed on MahaRERA.
Does Saibaba Sales Private Limited have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.