Sai Sankalp Developers
Deedo IDDD-ZZH8Of 2 registrations whose promised date has arrived, 0 kept it (0%). The rest ran a median 7 mo late.
Delivery record
2 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Nandanvan ColinaP52100014132 | Ambegaon Bk | Certificate Signed | 29 Mar 2021 | 30 Dec 2021 | +9 mo |
| Nandanvan ColinaP52100049350 | Ambegaon Bk | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | +5 mo* |
Sai Sankalp Developers, in questions
Does Sai Sankalp Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 7 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sai Sankalp Developers registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Sai Sankalp Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.