Sai Ganesh Builders
Deedo IDDD-HGDGOf 1 registration whose promised date has arrived, 0 kept it (0%). The rest ran a median 5 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| S M RoyalP52000053077 | Taloje Panchnad | Certificate Signed | 30 Jun 2026 | 30 Jun 2026 | +5 mo* |
| Innovative SymphonyPM1270002602719 | Taloja | Not on record | 30 Jun 2032 | — | On date |
Sai Ganesh Builders, in questions
Does Sai Ganesh Builders finish projects on time?
Of 1 MahaRERA registration whose promised completion date has arrived, 0 kept it (0%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sai Ganesh Builders registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 0 completed on MahaRERA.
Does Sai Ganesh Builders have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.