Sai Construction
Company or firm · 3 projects · 3 MahaRERA registrations · 1 reported completed
Projects33 RERA registrations
Completed1as reported on MahaRERA project pages
Kept RERA date100%3 of 3 past their proposed date, not extended
Median delay+0 movs RERA proposed date · 0 extended
Regulatory cases0MahaRERA orders and lists
Projects
Delay is measured against the RERA proposed completion date on the registration certificate.
| Project | Locality | RERA year | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|---|
| Shantaniwas Co-Op Housing SocietyP51600017884 | Deolaligaon | 2018 | Completed | 30 Mar 2022 | — | On date |
| Chhatrapati ChambersP51600033617 | Nashik (M Corp.) | 2022 | Not reported | 31 Dec 2025 | — | On date |
| Serenity ParkP51600048887 | Deolaligaon | 2023 | Not reported | 25 Nov 2025 | — | On date |
Delivery timeline
RERA proposed completion vs the latest revised date, per registration.
Track record notes
- 3 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
- No MahaRERA regulatory order or list names these registrations.
Regulatory cases across projects
None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology
