Deedo IDDD-FDD9Of 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 59 mo late.
Delivery record
1 of 2 registrations with dates moved or missed their RERA date · months late against the original promise
2 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sai Sagar Enclave VP50300013084 | Amravati (M Corp.) | Lapsed | 30 Dec 2021 | — | +59 mo* |
| Sai Sagar Enclave VIP50300016843 | Amravati (M Corp.) | Completed | 30 Mar 2024 | — | On date |
Sagar Pandharinath Bankar, in questions
Does Sagar Pandharinath Bankar finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 59 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sagar Pandharinath Bankar registered with MahaRERA?
2 projects under 2 MahaRERA registrations; 1 completed on MahaRERA.
Does Sagar Pandharinath Bankar have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.