Saffron Associates

Company or firm · 4 projects · 4 MahaRERA registrations

4Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
50%Kept RERA date1 of 2 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Saffron Tranquil LandscapeP51500002740Aurangabad (M Corp.)2017Not reported31 Jul 201930 Jan 2021+18 months
Saffron LandscapesP51500008765Aurangabad (M Corp.)2017Not reported31 Jul 2025—On date
Saffron Landscape Phase IP51500031063Satara (Ct)2021Not reported31 Dec 2026—On date
Saffron LandmarksP51500048247Satara (Ct)2022Not reported30 Jun 2027—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Saffron Tranquil Landscape+18 mo
  • Saffron LandscapesOn date
  • Saffron Landscape Phase IOn date
  • Saffron LandmarksOn date

Track record notes

  • 1 of 2 registrations whose RERA proposed completion date has passed was never extended beyond it.
  • Longest extension on record: 18 months, for Saffron Tranquil Landscape (P51500002740).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology