Sable Sanjivani Saswad Infrastructure Llp
Deedo IDDD-PWNDOf 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 9 mo late — longer than Maharashtra's 4 mo.
Delivery record
1 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Sangameshwar Phase AP52100022448 | Sasvad (M Cl) | Certificate Signed | 31 Dec 2022 | 15 Sep 2023 | +9 mo |
| Sangameshwar Villa PlottingP52100046150 | Sasvad (M Cl) | Certificate Signed | 31 Mar 2023 | 31 Mar 2023 | On date |
| Sangameshwar GoldP52100078664 | Sasvad (M Cl) | Certificate Signed | 15 May 2025 | 15 May 2025 | On date |
Sable Sanjivani Saswad Infrastructure Llp, in questions
Does Sable Sanjivani Saswad Infrastructure Llp finish projects on time?
Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 9 mo late. Across Maharashtra, 73% kept their date.
How many projects has Sable Sanjivani Saswad Infrastructure Llp registered with MahaRERA?
3 projects under 3 MahaRERA registrations; 3 completed on MahaRERA.
Does Sable Sanjivani Saswad Infrastructure Llp have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.