Sangameshwar Phase A

Certificate Signed

Sasvad (M Cl), Pune 412301 |Promoter: Sable Sanjivani Saswad Infrastructure LLP

24 Sep 2019Registered with MahaRERA
31 Dec 2022Promised completion
15 Sep 2023Revised completionPushed back 9 months
1Building
106Units registered35 booked (33%)
0MahaRERA listings and ordersNone found

Project summary

As registered with MahaRERA and published on its project page

Project type
Others
Status on MahaRERA
Certificate Signed
Buildings
1
Unit types
1BHK, 2BHK, Office space, Shop106 units in all
Address
17, 18, 19, Pune Saswad Road, SaswadPIN 412301
Designated bank account
17
Developed in phases
No

Registered transactions

No registered transactions matched to this project yetSales, resales, rentals and mortgages appear here once registered documents are matched to this project by evidence.

Completion timeline

Registration date, the completion date promised at registration, and any extension since

Completion pushed back 9 months

The latest completion date on record passed 3 years and 1 month ago.

Registered
24 Sep 2019
Promised
31 Dec 2022
Revised
15 Sep 2023

RERA registration

RegistrationRegisteredPromised completionRevised completionPromoterMahaRERA
P5210002244824 Sep 201931 Dec 202215 Sep 2023Sable Sanjivani Saswad Infrastructure LLPProject page

1 building

Buildings and wings named in the registration

BuildingSanctioned floorsUnits
Sangameshwar Phase A10106

Source: registration certificate annexures and MahaRERA's project page. “Floors with CC” counts floors covered by a commencement certificate.

Units and parking

35 of 106 units booked (33%), as the promoter reported to MahaRERA

1BHK · 51 units2BHK · 28 unitsOffice space · 12 unitsShop · 15 units
TypeCarpet areaUnitsBooked
1BHK37.17 sq m · 400 sq ft165
1BHK38.66 sq m · 416 sq ft299
1BHK42.94 sq m · 462 sq ft30
1BHK43.59 sq m · 469 sq ft10
1BHK43.77 sq m · 471 sq ft10
1BHK47.49 sq m · 511 sq ft11
2BHK50.37 sq m · 542 sq ft103
2BHK51.58 sq m · 555 sq ft168
Show all 36 unit rowsShow fewer unit rows
TypeCarpet areaUnitsBooked
2BHK55.3 sq m · 595 sq ft21
Office space13.11 sq m · 141 sq ft10
Office space14.31 sq m · 154 sq ft10
Office space20.2 sq m · 217 sq ft10
Office space20.22 sq m · 218 sq ft10
Office space21.07 sq m · 227 sq ft10
Office space21.46 sq m · 231 sq ft10
Office space22.44 sq m · 242 sq ft10
Office space23.24 sq m · 250 sq ft10
Office space26.02 sq m · 280 sq ft10
Office space32.97 sq m · 355 sq ft10
Office space41.7 sq m · 449 sq ft10
Office space42.58 sq m · 458 sq ft10
Shop12.92 sq m · 139 sq ft10
Shop13.13 sq m · 141 sq ft11
Shop13.29 sq m · 143 sq ft11
Shop18.77 sq m · 202 sq ft11
Shop19.61 sq m · 211 sq ft10
Shop20.17 sq m · 217 sq ft10
Shop20.26 sq m · 218 sq ft10
Shop20.35 sq m · 219 sq ft10
Shop22.4 sq m · 241 sq ft11
Shop22.49 sq m · 242 sq ft11
Shop23.23 sq m · 250 sq ft11
Shop24.35 sq m · 262 sq ft11
Shop26.58 sq m · 286 sq ft10
Shop28.16 sq m · 303 sq ft11
Shop34.57 sq m · 372 sq ft10

Source: MahaRERA project page, as the promoter filed it. Carpet areas are per unit.

Documents

2 documents held by Deedo, 81 filings listed on MahaRERA's project page

Registration certificate

Extension certificate

Finance

  • PAN CardPAN.PDF · uploaded 17 Sep 2019Source

Legal

  • OtherBrochure.pdf · uploaded 17 Sep 2019Source
  • Legal Title reportTitle Report.pdf · uploaded 17 Sep 2019Source
  • Declaration Form BForm B.pdf · uploaded 20 Sep 2019Source

Migrated

  • 1 PAN CardPAN.PDF · uploaded 17 Sep 2019Source
  • 1 Copy of the legal title reportTitle Report.pdf · uploaded 17 Sep 2019Source
Show all 83 documentsShow fewer documents

Migrated

  • 1 Copy of Layout Approval (in case of layout)Collector office NA Order.pdf · uploaded 17 Sep 2019Source
  • 1 Building Plan Approval / NA Order for plotted developmentBuilding Plan.PDF · uploaded 17 Sep 2019Source
  • 1 Commencement Certificates / NA Order for plotted developmentCommencement Certificate.pdf · uploaded 17 Sep 2019Source
  • 1 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 17 Sep 2019Source
  • 1 Engineer’s Certificate on Cost Incurred on Project (Form 2)FORM 2.pdf · uploaded 17 Sep 2019Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A)FORM 2A.pdf · uploaded 17 Sep 2019Source
  • 1 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 17 Sep 2019Source
  • 1 Proforma of Allotment letterAgreement.PDF · uploaded 17 Sep 2019Source
  • 2 Proforma of Allotment letterAllotment Letter.PDF · uploaded 17 Sep 2019Source
  • 1 OtherBrochure.pdf · uploaded 17 Sep 2019Source
  • 1 Details of encumbrancesSelf Declaration.pdf · uploaded 20 Sep 2019Source
  • 1 Declaration in FORM BForm B.pdf · uploaded 20 Sep 2019Source
  • 2 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 14 Feb 2020Source
  • 2 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 Reduced.pdf · uploaded 14 Feb 2020Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A)Form 2A Reduced.pdf · uploaded 14 Feb 2020Source
  • 2 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 Reduced.pdf · uploaded 14 Feb 2020Source
  • 2 Building Plan Approval / NA Order for plotted developmentRevised Plan Compressed.pdf · uploaded 15 Jan 2021Source
  • 3 Building Plan Approval / NA Order for plotted developmentRevised Plan Compressed.pdf · uploaded 15 Jan 2021Source
  • 2 Commencement Certificates / NA Order for plotted developmentSector 01 with A build CC 2059.pdf · uploaded 15 Jan 2021Source
  • 3 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 15 Jan 2021Source
  • 3 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form-2 Compressed.pdf · uploaded 15 Jan 2021Source
  • 3 Engineers Certificate on Quality Assurance (Form 2A)Form 2A Compressed.pdf · uploaded 15 Jan 2021Source
  • 3 CA Certificate on Project Cost & Fund withdrawal (Form 3)Chartered Accountant Certificate Compressed.pdf · uploaded 15 Jan 2021Source
  • 1 Declaration about Commencement CertificateSector 01 with A build CC 2059.pdf · uploaded 1 Jul 2021Source
  • 2 Declaration about Commencement CertificateCommencement Certificate.pdf · uploaded 1 Jul 2021Source
  • 4 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 2 Jul 2021Source
  • 4 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form- 2.pdf · uploaded 2 Jul 2021Source
  • 4 Engineers Certificate on Quality Assurance (Form 2A)Form-2A.pdf · uploaded 2 Jul 2021Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)Form-2A.pdf · uploaded 2 Jul 2021Source
  • 1 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 2 Jul 2021Source
  • 4 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 2 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2019-20)Form 5 2019-20.pdf · uploaded 2 Jul 2021Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)Form 5 2020-21.pdf · uploaded 2 Jul 2021Source
  • 5 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1.pdf · uploaded 29 Oct 2021Source
  • 5 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 29 Oct 2021Source
  • 5 Engineers Certificate on Quality Assurance (Form 2A)Form 2A.pdf · uploaded 29 Oct 2021Source
  • 2 Disclosure of sold/ booked inventorySOLD INVENTRY.pdf · uploaded 29 Oct 2021Source
  • 5 CA Certificate on Project Cost & Fund withdrawal (Form 3)FORM 3.pdf · uploaded 29 Oct 2021Source
  • 6 Architect’s Certificate of Percentage of Completion of Work (Form 1)fORM 1.pdf · uploaded 25 Feb 2022Source
  • 6 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2.pdf · uploaded 25 Feb 2022Source
  • 1 CERSAI detailsCREDAI CERTIFIACTE 21-22.pdf · uploaded 25 Feb 2022Source
  • 3 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 25 Feb 2022Source
  • 6 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3.pdf · uploaded 25 Feb 2022Source
  • 7 Architect’s Certificate of Percentage of Completion of Work (Form 1)Architect Certificate.pdf · uploaded 7 Jun 2022Source
  • 7 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERIS CERTIFICATE.pdf · uploaded 7 Jun 2022Source
  • 6 Engineers Certificate on Quality Assurance (Form 2A)FROM 2A.pdf · uploaded 7 Jun 2022Source
  • 2 Engineers Certificate on Quality Assurance (Form 2A FY 2020-21)FROM 2A.pdf · uploaded 7 Jun 2022Source
  • 4 Disclosure of sold/ booked inventorySOLD INVENTORY.pdf · uploaded 7 Jun 2022Source
  • 7 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA Certificate.pdf · uploaded 7 Jun 2022Source
  • 2 Annual Audit Report of Statutory CA (Form 5) (FY 2020-21)LLP RERA FORM 5.pdf · uploaded 8 Jun 2022Source
  • 8 Architect’s Certificate of Percentage of Completion of Work (Form 1)RERA- Form 1 Architect Certificate.pdf · uploaded 28 Sep 2022Source
  • 8 Engineer’s Certificate on Cost Incurred on Project (Form 2)RERA LLP FORM -2.pdf · uploaded 28 Sep 2022Source
  • 5 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 28 Sep 2022Source
  • 8 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3- CA CERTIFICATE RERA.pdf · uploaded 28 Sep 2022Source
  • 9 Architect’s Certificate of Percentage of Completion of Work (Form 1)ARCHITECHT CERTIFICATE.pdf · uploaded 16 Jan 2023Source
  • 9 Engineer’s Certificate on Cost Incurred on Project (Form 2)ENGINEERS CERTIFICATE.pdf · uploaded 16 Jan 2023Source
  • 6 Disclosure of sold/ booked inventorySOLD INVENTORY.pdf · uploaded 16 Jan 2023Source
  • 9 CA Certificate on Project Cost & Fund withdrawal (Form 3)CA_CERTIFICATE.pdf · uploaded 17 Jan 2023Source
  • 1 Annual Audit Report of Statutory CA (Form 5) (FY 2021-22)LLP RERA FORM 5.pdf · uploaded 17 Jan 2023Source
  • 10 Architect’s Certificate of Percentage of Completion of Work (Form 1)Form 1 Architect Certificate Reduced.pdf · uploaded 10 Apr 2023Source
  • 10 Engineer’s Certificate on Cost Incurred on Project (Form 2)Form 2 March 2023 Reduced.pdf · uploaded 10 Apr 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2021-22)FROM 2A.pdf · uploaded 10 Apr 2023Source
  • 7 Disclosure of sold/ booked inventorySold Inventory Reduced.pdf · uploaded 10 Apr 2023Source
  • 10 CA Certificate on Project Cost & Fund withdrawal (Form 3)Form 3 March 2023 Reduced.pdf · uploaded 10 Apr 2023Source
  • 1 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentCompletion cum Occupancy Certificate.pdf · uploaded 28 Jun 2023Source
  • 2 Occupancy Certificate/ Completion Certificate/ Architect's certificate of completion for plotted developmentPhase-1 A Building -final compention certificate.pdf · uploaded 20 Jul 2023Source
  • 1 Engineers Certificate on Quality Assurance (Form 2A FY 2022-23)Form 2A- After Work .pdf · uploaded 16 Sep 2023Source
  • 8 Disclosure of sold/ booked inventorySold Inventory.pdf · uploaded 16 Sep 2023Source
  • 3 Architect’s Certificate on Completion of Project (Form 4)FORM-4 LLP (1).pdf · uploaded 3 Oct 2023Source

Technical

  • DocumentCollector office NA Order.pdf · uploaded 17 Sep 2019Source
  • DocumentBuilding Plan.PDF · uploaded 17 Sep 2019Source
  • DocumentRevised Plan Compressed.pdf · uploaded 15 Jan 2021Source
  • DocumentRevised Plan Compressed.pdf · uploaded 15 Jan 2021Source

Technical (Architect)

  • DocumentForm 1 Architect Certificate Reduced.pdf · uploaded 10 Apr 2023Source

Technical (Engineer)

  • DocumentForm 2 March 2023 Reduced.pdf · uploaded 10 Apr 2023Source

Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.

Regulatory record

Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.

Source: MahaRERA regulatory lists and orders, checked against each RERA number.

Land

In Sasvad (M Cl), Purandhar taluka

Survey, CTS, gat or plot numbers

171819

Boundaries

North
Proposed Building
South
Internal Road
East
Transformer And Stp
West
Open Space

Source: registration certificates and MahaRERA's project page, as stated there.

Professionals

Architects, engineers, chartered accountants and agents named on the registration

RoleNameRegistration no.
ArchitectMilind Panchal—
Chartered accountantSarang Rajhans—
EngineerSagar Doiphode—
OtherAdv Abhishek Lagoo—
OtherBipin Dorle—
OtherNot Applicable—
OtherRahul Darvekar—

Source: MahaRERA project page. Contact details are not shown.