S K Developers
Deedo IDDD-P4AXOf 2 registrations whose promised date has arrived, 1 kept it (50%). The rest ran a median 14 mo late — longer than Maharashtra's 4 mo.
Delivery record
2 of 3 registrations with dates moved or missed their RERA date · months late against the original promise
3 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Galaxy GardenP52000006725 | Pashane | Certificate Signed | 31 Dec 2019 | 30 Dec 2021 | +24 mo |
| Galaxygarden Plot No 2 And Plot No 4P52000018423 | Pashane | Certificate Signed | 31 Mar 2026 | 31 Mar 2026 | On date |
| Galaxy GardenP52000079527 | Pashane | Certificate Signed | 31 Dec 2030 | 30 Apr 2031 | +4 mo |
S K Developers, in questions
Does S K Developers finish projects on time?
Of 2 MahaRERA registrations whose promised completion date has arrived, 1 kept it (50%). The rest ran a median 14 mo late. Across Maharashtra, 73% kept their date.
How many projects has S K Developers registered with MahaRERA?
2 projects under 3 MahaRERA registrations; 2 completed on MahaRERA.
Does S K Developers have MahaRERA regulatory cases?
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.