Galaxy Garden
Completion due Dec 2030Pashane, Raigarh 410201 |Promoter: S K Developers
Project summary
As registered with MahaRERA
- RERA registrations
- 2
- Phases
- 2
Location
Coordinates as published by MahaRERA
Also registered as
Unit mix, parking, construction progress and the project's professionals come from that page. You can open it on MahaRERA (it asks for a CAPTCHA).
Latest registered deals
Completion timeline
Registration date, the completion date promised at registration, and any extension since
Completion pushed back 2 years
P52000006725The latest completion date on record passed 4 years and 10 months ago.
- Registered
- 16 Aug 2017
- Promised
- 31 Dec 2019
- Revised
- 30 Dec 2021
Completion promised for 31 Dec 2030
P52000079527- Registered
- 10 Mar 2025
- Promised
- 31 Dec 2030
2 RERA registrations
| Registration | Registered | Promised completion | Revised completion | Promoter | MahaRERA |
|---|---|---|---|---|---|
| P52000006725 | 16 Aug 2017 | 31 Dec 2019 | 30 Dec 2021 | S K Developers | Project page |
| P52000079527 | 10 Mar 2025 | 31 Dec 2030 | — | S K Developers | Project page |
Documents
3 documents held by Deedo
Registration certificate (2)
Source: Certificates, orders and filings published by MahaRERA. Filings that can't be opened here are listed as they appear on MahaRERA's project page.
Regulatory record
Deedo hasn't found this project's RERA number in any MahaRERA list or order it has read: deregistered, abeyance, NCLT, quarterly-report non-compliance, revoked, regulatory and suo motu orders.
Source: MahaRERA regulatory lists and orders, checked against each RERA number.
Land
In Pashane
Survey, CTS, gat or plot numbers
Source: registration certificates, as stated there.