S K Buildcon

Company or firm · 3 projects · 4 MahaRERA registrations

3Projects4 RERA registrations
0Completedas reported on MahaRERA project pages
67%Kept RERA date2 of 3 past their proposed date, not extended
+0 moMedian delayvs RERA proposed date · 1 extended
0Regulatory casesMahaRERA orders and lists

Projects

Delay is measured against the RERA proposed completion date on the registration certificate.

ProjectLocalityRERA yearStatusProposedRevisedDelay
Om ParadiseP52100002744Pimpri Chinchawad (M Corp.)2017Not reported31 Dec 2017—On date
Indraa ParkP52100004605Pimpri Chinchawad (M Corp.)2017Not reported30 Dec 2021—On date
Om ParadiseP52100008127Pimpri Chinchawad (M Corp.)2017Not reported30 Dec 202131 May 2022+5 months
Primrose ParkP52100048534Pune (M Corp.)2023Not reported31 Dec 2026—On date

Delivery timeline

RERA proposed completion vs the latest revised date, per registration.

  • Om ParadiseOn date
  • Indraa ParkOn date
  • Om Paradise+5 mo
  • Primrose ParkOn date

Track record notes

  • 2 of 3 registrations whose RERA proposed completion date has passed were never extended beyond it.
  • Longest extension on record: 5 months, for Om Paradise (P52100008127).
  • No MahaRERA regulatory order or list names these registrations.

Regulatory cases across projects

None on recordNo MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Methodology