S K Buildcon

Deedo IDDD-BN5Z

Of 3 registrations whose promised date has arrived, 2 kept it (67%). The rest ran a median 5 mo late — longer than Maharashtra's 4 mo.

Projects34 RERA registrations
Kept RERA date67%Maharashtra: 73%
Median delay5 mowhen late · Maharashtra: 4 mo
First sales on record0registered first-sale deeds matched so far
Regulatory cases0none on record

Delivery record

2 of 4 registrations with dates moved or missed their RERA date · months late against the original promise

4 registrations with dates · Source: MahaRERA registration and extension certificates

Regulatory cases

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.

Projects

Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.

ProjectLocalityStatusProposedRevisedDelay
Om ParadiseP52100002744KiwaleCertificate Signed31 Dec 201731 Dec 2017On date
Indraa ParkP52100004605Pimpri Chinchawad (M Corp.)Certificate Signed30 Dec 202130 Dec 2021On date
Om ParadiseP52100008127KiwaleCertificate Signed30 Dec 202131 May 2022+5 mo
Primrose ParkP52100048534Pune (M Corp.)Certificate Signed31 Dec 202630 Apr 2027+4 mo

S K Buildcon, in questions

Does S K Buildcon finish projects on time?

Of 3 MahaRERA registrations whose promised completion date has arrived, 2 kept it (67%). The rest ran a median 5 mo late. Across Maharashtra, 73% kept their date.

How many projects has S K Buildcon registered with MahaRERA?

3 projects under 4 MahaRERA registrations; 3 completed on MahaRERA.

Does S K Buildcon have MahaRERA regulatory cases?

No MahaRERA deregistration, abeyance, NCLT, revocation or other order names its registrations.

SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology