Individual promoter · first RERA registration 2018
Rupali Pramod Gharde
Deedo IDDD-R4N6Of 3 registrations whose promised date has arrived, 3 kept it (100%).
Projects55 RERA registrations
Kept RERA date100%Maharashtra: 73%
Median delay4 mowhen late · Maharashtra: 4 mo
Flats sold, all time0registered sale deeds
Regulatory cases0none on record
2 registrations of 5 ran past the RERA date
Months late against the original RERA promise, per registration
5 registrations with dates · Source: MahaRERA registration and extension certificates
Regulatory cases
No MahaRERA deregistration, abeyance, NCLT, revocation or other order names these registrations.
Projects
Delay is measured against the RERA proposed completion date on the registration certificate; * still open: the date has passed and MahaRERA shows no completion yet.
| Project | Locality | Status | Proposed | Revised | Delay |
|---|---|---|---|---|---|
| Dev PlazaP50500018041 | Pawangaon | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| Dev HeightsP50500018109 | Pawangaon | Certificate Signed | 30 Jun 2027 | 30 Oct 2027 | +4 mo |
| Prabha City Phase-IIP50500018616 | Pawangaon | Completed | 30 Dec 2023 | — | On date |
| Prabha City Lotus-2P50500021582 | Nagpur (M Corp.) | Lapsed | 30 Jun 2021 | — | On date |
| Prabha City Lotus-3P50500025707 | Nagpur (M Corp.) | Certificate Signed | 30 Jun 2023 | 30 Jun 2023 | On date |
SourcesMahaRERA project pages · registration and extension certificates · regulatory lists and ordersPersonal details of promoters are not shown.Report a problemMethodology