RegisteredExtendedMahaRERA status: Certificate Signed

P50500018041

Dev Plaza · Pawangaon, Nagpur · Rupali Pramod Gharde

Promised for 30 Jun 2027, extended to 30 Oct 2027, which is still ahead.

The revised date is 4 months after the original promise.

What to watch

Facts from the record. A flag is a reason to ask questions, not a verdict.

  • Caution: Completion date extended from 30 Jun 2027 to 30 Oct 2027.

Documents 18

Registration certificate12 Aug 2026View
OtherView
Commencement certificateView
OtherView
Form BView
Form 1View
Allotment letterView
Form 1View
Show all 18 documents
OtherView
OtherView
Title reportView
Encumbrance detailsView
Encumbrance detailsView
Layout planView
Form 1View
Form 1View
OtherView
Form 1View

Orders 0

No MahaRERA order or list names this number.

Questions about P50500018041

Is Dev Plaza delayed?

Its completion moved from 30 Jun 2027 to 30 Oct 2027; the revised date has not passed yet.

How many extensions has it had?

Deedo holds 0 extension certificates for P50500018041. The completion date moved from 30 Jun 2027 to 30 Oct 2027.

Who is the promoter?

MahaRERA records Rupali Pramod Gharde as the promoter of P50500018041.

Is it on any MahaRERA regulatory list?

No MahaRERA order or list that Deedo holds names P50500018041.

Answers are generated from the record.

Data through23 Oct 2026, 01:46SourcesMahaRERA project register · registration and extension certificates · regulatory lists and ordersMethodology